There is panic on the home front in SA. Prices are falling as terrified sellers flood the market.
Kempton Park in the dark
Article By:
Thu, 24 Apr 2008 13:42
Restoring power to the Kempton Park CBD could take a week, the
Ekuhruleni municipality said on Thursday.
"We have a minimum period of five days for repairs and a maximum of
up to ten days [from the date of the incdent]. We are trying to do the
minimum," said Ekuhruleni spokesperson Zweli Dlamini.
This followed a fire at a substation on Tuesday which plunged the
area into darkness
The areas to be affected include Kempton park extension 1, 2 and
four; the CBD, Allen Grove, Adleen and Spartan.
The municipality were going to replace the transformer and panel
that caught fire and repair the structure that housed them.
Dlamini said they were "very optimistic" that they would be able to
meet the deadline.
About 75 percent of power had been restored to the affected areas
apart from the CBD.